Urgent repairs and renovations demanded a resourceful partner.
When ConAgra business requirements called for a near complete makeover of two facilities in Garner, North Carolina and Sylvester, Georgia, they turned to a longtime strategic partner: Haskell. Through past experience, they knew we could meet the challenges of any project even when faced with the tightest timeline. In fact, within 24 hours of the assignment, we dispatched team members to two site locations and began design and start-up in earnest.
 
We dispatched design and construction teams within a day.
The projects’ fast-track permitting, demolition, construction, food-grade requirements and site management required tight coordination and seamless communication. Our teams built walls, repaired structures, installed a roof, replaced HVAC, refinished floors and set new equipment. When time or projects demanded, we worked around the clock to maintain the schedule.
 
Production began quickly and with greater efficiency.
Haskell project teams worked tirelessly to deliver modern, effective production facilities for ConAgra. Despite an evolving scope and multi-state site locations, the projects were complete within six months. What’s more, unexpected and important customer needs did not translate into exorbitant costs. We completed both projects on time and on budget.
LOCATION
Sylvester, Georgia, USA
DETAILS
Deployed design and construction resources and formulated turnkey teams within 24 hours of assignment.
 
Teams led quick-response shut down, design, permitting, construction, equipment installation, and start-up.
 
When ultra-fast demands arose Haskell teams worked around the clock.

Architect/Engineer
Haskell

Start Date
June 2011

Completion Date
October 2011